PMP Process Group Flashcards: Initiate, Plan, Execute, Monitor, Close (2026)
PMP process-group language: initiating through closing, the charter, progressive elaboration, and what a baseline is allowed to do.
Confirm items against the current ASCM or PMI content outline. This desk is an independent study aid and is not an official item bank.
Study desk
Initiating
The process group that authorizes the project or a phase and identifies the initial stakeholders. The charter is its signature output.
Flip cards, the timed match, and the quiz open in this panel. The full glossary below is ready either way.
Full glossary
Every term, pronunciation, definition, memory hook, and exam trap is written out here so you can review the whole set or print it.
Initiating
ih-NISH-ee-ay-ting
The process group that authorizes the project or a phase and identifies the initial stakeholders. The charter is its signature output.
Mnemonic. Initiating says the work may start and names who is accountable for it.
Exam trap. Initiating is not the place for the detailed schedule. If the stem is still asking whether the project should exist, you are not in planning yet.
The process group that performs the work in the plan, acquires and develops the team, and carries out the procurement and stakeholder actions.
Mnemonic. Executing spends the effort the plan described.
Exam trap. A status meeting that only compares actuals to the baseline is monitoring and controlling, even if it feels like doing the work. Look for the verb: performing versus comparing.
The process group that tracks performance, compares it with the baseline, and recommends or approves changes, corrective actions, and defect repairs.
Mnemonic. This group watches the variance and decides what is allowed to change.
Exam trap. Do not implement a scope change inside executing because the customer asked in the hallway. The controlling process evaluates it against the baseline first.
The process group that confirms the work is accepted, closes contracts, releases people, and archives lessons and records.
Mnemonic. Closing is acceptance plus handover plus memory. It is not the party.
Exam trap. A phase can close while the project continues. The trap is waiting until the entire project ends before any closing process is allowed to run.
The document that formally authorizes the project, names the project manager, and states the high-level objectives, constraints, and success idea.
Mnemonic. The charter is the permission slip and the name on the door.
Exam trap. The charter is not the project management plan. If it already contains the full WBS and the detailed budget, the question has skipped ahead.
The approved version of scope, schedule, and cost (and the plans that describe them) against which performance is compared.
Mnemonic. The baseline is the line you measure against, not the line you silently redraw.
Exam trap. Updating the baseline without an approved change hides variance. The exam wants the change first, then the new baseline, and it wants the old variance preserved in the record.